This notice is the first of two, and only addresses the shutdown on Tues May 30.  The south wing (Phase 1 space) will be without power from Tues 5/30 through June 3, the other spaces will be back on at 7:30 am.

There will be a 2nd notice about the second, longer, shutdown on Sat Jun 3.

Day 1 - Tuesday May 30

  *   6am shut down main power to Batchelor and Keen Hall (4hrs)
  *   10am reinstate power to Batchelor Hall main building and Keen Hall (Phase 1 spaces in Batchelor hall with remain off for 1 week)

Day 5 - Saturday Jun 3

  *   4am shut down and disconnect main feeds to Batchelor Hall and Keen hall (15hr shut down)
  *   8pm reinstate new main power to Batchelor and Keen Hall from generator yard

The contractor has a list of all equipment that will need generator power during the 15-hr shutdown.

Patty


Begin forwarded message:

From: Facilities <facilities at ucr.edu<mailto:facilities at ucr.edu>>
Subject: PLANNED ELECTRICAL SHUTDOWN NOTIFICATION MULTIPLE BUILDINGS — 5/30
Date: May 25, 2023 at 3:46:16 PM PDT


[cid:image003.png at 01D98F20.0802D8B0]
PLANNED SHUTDOWN NOTIFICATION

DATE & TIME
•   Tuesday, May 30 from 5:15 am to 7:30 am for all listed buildings
•   Tuesday, May 30 from 5:15 am to Saturday, June 3 at 8:00 pm for Batchelor Hall, South Hall
LOCATION
1.       Anthropology Trailer
2.       Batchelor Hall
3.       Botanical Gardens
4.       Boyden Hall
5.       College Building North
6.       College Building South
7.       Electric Vehicle Chargers – Lot 9
8.       Facilities Annex A
9.       Facilities Annex B
10.   Fawcett Laboratory
11.   Greenhouses 1, 2, 3, and 18, 19, 20, 21
12.   Greenhouses 51 and 52
13.   Growth Facilities Chamber — GFC-1
14.   Growth Trailer Near Zemon Hall
15.   Herbarium
16.   Keen Hall
17.   Lath House 4 and 8
18.   Radio Tower
19.   SPI
20.   SPN3
21.   Steam Plant — TES Tanks 1, 2, and 3 Communications
22.   Superintendent’s Cottage
23.   University Office Building
WHAT TO EXPECT
There will be no power during these times. Electrical equipment, lights, and elevators will be impacted.
PURPOSE A power shutdown is required to replace electrical equipment and bring in new generator power for the Batchelor Hall construction project.

Occupants with sensitive research equipment should take the following precautions:
•         If you have sensitive research equipment or systems you know can be impacted by power interruption and you have not connected them to uninterrupted power devices (UPS) and surge protectors, please plan to disconnect and turn off equipment for the duration to avoid any damage.
•         Additional information on how to power down your equipment may be found from our partners at EH&S: https://ehs.ucr.edu/laboratory/utilities.
CONTACT
John Franklin, Project Manager
(951) 827-1270 / john.franklin at ucr.edu<mailto:john.franklin at ucr.edu>
Client Support Services Team
(951) 827-4214 / facilities at ucr.edu<mailto:facilities at ucr.edu>
In an ongoing effort to keep our distribution lists accurate and updated, if someone needs to be included or removed on this type of notification, please use this form<https://ucriverside.az1.qualtrics.com/jfe/form/SV_57mfrlWj7IX9kYm> to add their contact information. If you have any questions or concerns, please email facilities at ucr.edu<mailto:facilities at ucr.edu>.
UCR FACILITIES SERVICES | FACILITIES.UCR.EDU<http://facilities.ucr.edu/>

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.ucr.edu/pipermail/bhoccupants/attachments/20230526/626e5f17/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.png
Type: image/png
Size: 5948 bytes
Desc: image003.png
URL: <https://lists.ucr.edu/pipermail/bhoccupants/attachments/20230526/626e5f17/attachment-0001.png>


More information about the Bhoccupants mailing list