[Bhoccupants] FW: 950464 Batchelor Hall - Construction Update

April Meinzer april.meinzer at ucr.edu
Thu Jul 21 10:02:51 PDT 2022


ALL BATCHELOR HALL OCCUPANTS AND DEPARTMENT LEADERSHIP,



Please be advised that the following activities will be occurring at the Batchelor Hall Building for the week of July 25, 2022, through July 29, 2022.



            Site, Roof and Basement:

·             Research and Identification of Mechanical, Electrical & Plumbing Piping.

·             Setting Racks for Plumbing Piping

·             Shutdown of Steam System

·             Rebuilding Steam PRV Station





Area A (Main Building):

·          Install Anchors for Conduit Runs in Basement.

·          Install Plumbing Piping in Basement.

·          Preparation and Planning for Mechanical Piping Systems.

·          Installing Plumbing and Electrical in Room 2163.

·          Install of Fan Coil Units in Room 2163

·          Research in Rooms for Planning Duct Routing



Area B (South Building):

·          Install Conduit in Corridors for New Lights.

·          Install Fire Alarm in Labs.

·          Install New Ductwork.

·          Install Fume Hood Exhaust.

·          Relocation of Industrial Cold Water Piping



We will be performing trenching for the installation of underground conduit work in Parking Lot 11 for the week of August 1, 2022 through August 26. Please see the attached Method of Procedure and plan.  Parking will not be affected at this time.  We will notify you in advance if this changes.

If you have any questions or concerns please feel free to email me or John Franklin (john.franklin at ucr.edu<mailto:john.franklin at ucr.edu> or call 951-203-7910).

The UCR Batchelor Hall Team recognizes that construction activities will at times pose inconveniences and disruption to the building occupants. We thank you for your patience during the construction of this project.


Vilma C. Kern
PROJECT MANAGER

[cid:image001.png at 01D89CE8.A8635EE0]

UNIVERSITY OF CALIFORNIA, RIVERSIDE
1223 UNIVERSITY | AVE SUITE 240 | RIVERSIDE CA 92507
P: 951-827-2464 | C: 951-534-2203 | vilma.kern at ucr.edu<mailto:vilma.kern at ucr.edu>

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.ucr.edu/pipermail/bhoccupants/attachments/20220721/ba02fdb4/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 3103 bytes
Desc: image001.png
URL: <https://lists.ucr.edu/pipermail/bhoccupants/attachments/20220721/ba02fdb4/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: ConstructionUpdate_2022-07-21.pdf
Type: application/pdf
Size: 1047183 bytes
Desc: ConstructionUpdate_2022-07-21.pdf
URL: <https://lists.ucr.edu/pipermail/bhoccupants/attachments/20220721/ba02fdb4/attachment-0001.pdf>


More information about the Bhoccupants mailing list