<font size=3 color="#0000FF"><b>TO:<x-tab> </x-tab>BIOLOGY
LAB PERSONNEL<br>
<x-tab> </x-tab>CBN LAB
PERSONNEL - SPIETH<br>
<x-tab> </x-tab>BIO GRAD
STUDENTS<br>
<x-tab> </x-tab>CBN GRAD
STUDENTS<br><br>
</b></font><font size=3>After conferring with all interested parties, the
floor abatement/replacement project in the Spieth basement (including
vivarium) will proceed as planned. Barring unforeseen events, the
schedule of work is as follows:<br><br>
<b><u>Damaged floor removal and abatement </u> (8-hour shift each
night)<br><br>
</b>Phase #1 -- West entrance to double doors (vivarium) will start
on 7-21-05 at 5:00 PM.<br><br>
Phase #2 -- Double doors to Spieth 339 (including 330) will start on
7-22-05 at 5:00 PM.<br><br>
Phase #3 -- Spieth 339 to 344 will start on 7-25-05 at 5:00 PM.<br><br>
Phase #4 -- Spieth 344 to stairwell will start on 7-26-05 at 5:00
PM.<br><br>
Physical Plant was successful in obtaining the services of a flooring
contractor that is willing to accommodate our schedule by performing the
work as quickly as possible after regular business hours. The
schedule is as follows:<br><br>
<b><u>West portion of floor between machine shop and vivarium
doors:<br><br>
</u></b>Phase
#1<x-tab> </x-tab>Wednesday,
July 27<x-tab> </x-tab>5:00 PM - 3:00
AM <br>
<x-tab> </x-tab><x-tab> </x-tab>Thursday,
July 28<x-tab> </x-tab>5:00 PM -
3:00 AM<br><br>
<br>
<b><u>Vivarium work will be conducted on three 10-hour shifts during the
weekend:<br><br>
</u></b>Phase
#2<x-tab> </x-tab>Friday,
July
29<x-tab> </x-tab><x-tab> </x-tab>5:00
PM - 3:00 AM<br>
Phases
#3<x-tab> </x-tab>Saturday, July
30<x-tab> </x-tab>3:00 PM - 1:00
AM<br>
Phase
#4<x-tab> </x-tab>Sunday,
July
31<x-tab> </x-tab><x-tab> </x-tab>3:00
PM - 1:00 AM<br>
(Area covered roughly corresponds to abatement phases above.)<br><br>
In an effort to prevent exposure of fumes to animals, HVAC mechanics will
alter ventilation to make the hallway negative with respect to animal
rooms. Ventilation changes may affect temperature control
therefore, temperature alarms monitoring will be suspended during the
course of the project. Physical Plant has obtained MSDS for
materials used during the abatement and floor install activities; I will
have copies available for your analysis.<br><br>
Regards, Dan<br>
</font><x-sigsep><p></x-sigsep>
<font size=2 color="#008000">_____________________________________________
<br>
</font><font face="Times New Roman, Times" size=5 color="#0000FF"><b><i>Dan
Rios<br>
</i></font><font size=2 color="#008000">Facilities Coordinator/Laboratory
Safety
Officer<x-tab> </x-tab>
<br>
Departments of:<x-tab> </x-tab><br>
<x-tab> </x-tab>Biology<x-tab> </x-tab><br>
<x-tab> </x-tab>Cell
Biology & Neuroscience <br>
<x-tab> </x-tab>UC Natural
Reserves System<br>
Spieth
312
<x-tab> </x-tab><br>
University of California<br>
Riverside, California 92521 <br><br>
</font><font size=2 color="#800000">voice: 951-827-3600 <br>
fax: 951-827-4286 <br>
email: daniel.rios@ucr.edu<br>
</font><font size=2 color="#008000"><a href="http://www.biology.ucr.edu/" eudora="autourl">http://www.biology.ucr.edu/</a></font><font size=3>
</font></b></body>
</html>